File #: 15-1200    Version: 1 Name: Streetscape Change Order No 1
Type: Resolution Status: Filed
File created: 6/16/2015 In control: Engineering
On agenda: 9/2/2015 Final action: 9/2/2015
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( X ) Amending Type of Service: Change Order/Amend Resolution Purpose: Citywide Streetscape: Mt. Prospect Avenue, Lower Broadway and Bloomfield Avenue Entity Name: Berto Construction, Inc Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065 Contract Amount: $751,698.07 (Change Order Amount) Funding Source: UEZ & Street Construction Fund Contract Period: End Date: October 31, 2015 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Original contract amount $4,933,902.47 + Change Order No.1 $751,698.07= New contact amount $5,685,600.54.
Sponsors: Council of the Whole
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( X ) Amending
Type of Service: Change Order/Amend Resolution
Purpose: Citywide Streetscape: Mt. Prospect Avenue, Lower Broadway and Bloomfield Avenue
Entity Name: Berto Construction, Inc
Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065
Contract Amount: $751,698.07 (Change Order Amount)
Funding Source: UEZ & Street Construction Fund
Contract Period: End Date: October 31, 2015
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original contract amount $4,933,902.47 + Change Order No.1 $751,698.07= New contact amount $5,685,600.54.
body

WHEREAS, Resolution No. 7R4-H, adopted August 7, 2013, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 03-2011R, Citywide Streetscape: Mt. Prospect Avenue, Lower Broadway and Bloomfield Avenue, with Berto Construction, Inc., 625 Leesville Avenue, Rahway, New Jersey 07065, for the amount of $4,933,902.47; and

WHEREAS, the Department of Engineering needs to increase and decrease existing quantities, and add new contract items due to unforeseen conditions. During construction additional increases and new construction items, and decreases were identified relating to curb and sidewalk, drainage, traffic signal conduits, tree removals, basement vaults, and resurfacing that were not identified during design because they were unforeseen and could not be anticipated when the design of this project took place; and

WHEREAS, change orders to change the quantity or character of goods provided or services performed from that originally specified or estimated and to correspondin...