File #: 16-0056    Version: 1 Name: McClellan St Design - Chnage Order # 3
Type: Resolution Status: Filed
File created: 1/12/2016 In control: Engineering
On agenda: 3/2/2016 Final action: 3/2/2016
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( X ) Amending Type of Service: Professional Services Contract Purpose: McClellan Street Underpass Roadway and Drainage Improvements Final Design, Change Order No. 3 Entity Name: Parsons Brinckerhoff, Inc. Entity Address: 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102 Contract Amount: $0.00 Funding Source: N/A Contract Period: Extend the contract period through February 1, 2017 Contract Basis: ( ) Bid ( ) State Vendor ( X ) Prof. Ser. ( ) EUS ( ) Fair & Open ( X ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Addition Information: Original contract amount of $1,091,849.92 and termination date of January 15, 2014. Change Orders No. 2 & 3 extended termination dates by one year each, with no increase in contract amount.
Sponsors: John Sharpe James, Luis A. Quintana
Related files: 19-1726
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( X ) Amending
Type of Service: Professional Services Contract
Purpose: McClellan Street Underpass Roadway and Drainage Improvements Final Design, Change Order No. 3
Entity Name: Parsons Brinckerhoff, Inc.
Entity Address: 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102
Contract Amount: $0.00
Funding Source: N/A
Contract Period: Extend the contract period through February 1, 2017
Contract Basis: ( ) Bid ( ) State Vendor ( X ) Prof. Ser. ( ) EUS
( ) Fair & Open ( X ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Original contract amount of $1,091,849.92 and termination date of January 15, 2014. Change Orders No. 2 & 3 extended termination dates by one year each, with no increase in contract amount.
body

WHEREAS, Resolution 7R4-B, adopted October 17, 2012, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 06-2012PS, McClellan Street Underpass Roadway and Drainage Improvements Final Design, with Parsons Brinckerhoff, Inc., 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102, for the amount of $1,091,849.92; and

WHEREAS, a 'Notice to Proceed' was issued dated January 16, 2013, specifying January 16, 2013 as the effective date of the contract, terminating on January 15, 2014; and

WHEREAS, Resolution 7R4-B, adopted March 5, 2014, authorized the Director of the Department of Engineering to issue and execute Change Order No. 1/Contract Amendment No. 1, to Contract #06-2012PS, McClellan Street Underpass Roadway and Drainage Improvements Final Design, for a one (1) year extension of term of the contract, from January 15, 2014 to February 1, 2015; and

WHEREAS, Resolution 7...