Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order/Amend Resolution 7R12-c adopted on February 6, 2014 Purpose: Execute Contract Close Out and Final Quantities Change Order No. 01 Entity Name: Spiniello Companies Entity Address: 354 Eisenhower Parkway, Livingston, New Jersey 07039 Contract Amount: $7,726,500.00 (Original Contract Amount) - $686,605.70 (Contract Amount Reduced) = $7,039,894.30. Funding Source: Water and Sewer Utility Capital Budget Contract Period: 320 Calendar Days until Final Completion Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Original Contract Amount: $7,726,500.00, Reduced for Unused Quantities: $695,746.50, Credit in the amount of: $600.00, Increa...
Sponsors: Council of the Whole
Related files: 14-0061
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Resolution 7R12-c adopted on February 6, 2014
Purpose: Execute Contract Close Out and Final Quantities Change Order No. 01
Entity Name: Spiniello Companies
Entity Address: 354 Eisenhower Parkway, Livingston, New Jersey 07039
Contract Amount: $7,726,500.00 (Original Contract Amount) - $686,605.70 (Contract Amount Reduced) = $7,039,894.30.
Funding Source: Water and Sewer Utility Capital Budget
Contract Period: 320 Calendar Days until Final Completion
Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Contract Amount: $7,726,500.00, Reduced for Unused Quantities: $695,746.50, Credit in the amount of: $600.00, Increase for additional work: $1,935.00, Increase for Settlement: $7,805.80, Net Amount of $686,605.70 To Be Reduced from the Contract Amount, Resulting Final Contract Amount: $7,039,894.30
Final Quantities Change Order and Contract Close-Out reducing the total contract amount by $686,605.70.
body

WHEREAS, Resolution 7R12-c dated February 2, 2016, authorized the award of Contract 08-WS2009 Brick Sewer Rehabilitation Program Phase VI (H) Sewer Rehabilitation, Spiniello Companies, 354 Eisenhower Parkway, Livingston, New Jersey 07039, in the amount of $7,726,500.00, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, Contract 08-WS2009 was completed with a total of $695,746.50 to be reduced for unused quantities, a credit of $600.00, an increase for additional work of $1,935.00 and an increase for a settlement of $7,805.80 with a net amount of $686,605.70 to be reduced from the total contract amount; and

WHEREAS, Contract 08-W...