Type of Service: Change Order/Amend Resolution 7R12-bNovember 17, 2014
Purpose: Execute Contract Close out and Final Quantities Change Order No. 01 for Repairs to Cedar Grove Reservoir Dams Contract 08-WS2012
Entity Name: Ritacco Construction Inc.
Entity Address: 10 Lawrence Street, Belleville, New Jersey 07109
Contract Amount: Original Contract Amount: $1,868,578.75, Increase for additional work: $109,441.81, Resulting Final Contract Amount: $1,978,020.56
Funding Source: Water and Sewer Utility Capital Budget
Contract Period: 270 Calendar Days to Final Completion extended by 400 days
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Final Quantities Change Order and Contract Close-Out which increases the total Contract by $109,441.81, and extends the completion time by 400 calendar days.
body
WHEREAS, Resolution 7R12-b dated November 17, 2014, authorized the award of Contract 08-WS2012 Repairs to Cedar Grove Reservoir Dams to, Ritacco Construction, Inc., 10 Lawrence Street, Belleville, New Jersey 07109, in the amount of $1,868,578.75, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and
WHEREAS, during the course of the project, Ritacco Construction, Inc. encountered unforeseen conditions, the most significant being multiple work stoppages due to legal challenges raised by the Township of Cedar Grove against the City of Newark; wherein the City was forced to litigate and defend its interests, and the New Jersey Superior Court subsequently ruled in the City's favor finding the City within its rights to continue its work under the Project; and
WHEREAS, these unforeseen conditions and work stoppages due to...