File #: 17-1073    Version: 1 Name: Utility Engineering and Construction Agreement Route 280 WB Ramp Over First and Orange Streets, Newark Subway and NJ Transit
Type: Resolution Status: Adopted
File created: 5/24/2017 In control: Water Sewer Utility
On agenda: 9/7/2017 Final action: 9/7/2017
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Intergovernmental Agreement Purpose: Utility Engineering and Construction Agreement Rt. 280 WB Ramp Over First and Orange Streets, Newark Subway and New Jersey Transit Entity Name: New Jersey Department of Transportation Entity Address: Post Office Box 600, Trenton, New Jersey 08625-0600 Contract Amount: N/A Funding Source: New Jersey Department of Transportation Contract Period: Until Completion of State Project Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient (X) n/a Additional Information: No municipal funds are required or will be spent under this agreement
Sponsors: Mildred C. Crump, Eddie Osborne

Title

Dept/ Agency:  Water and Sewer Utilities

Action:  (   ) Ratifying     (X) Authorizing     (  ) Amending

Type of Service: Intergovernmental Agreement

Purpose: Utility Engineering and Construction Agreement Rt. 280 WB Ramp Over First and Orange Streets, Newark Subway and New Jersey Transit

Entity Name:  New Jersey Department of Transportation

Entity Address:  Post Office Box 600, Trenton, New Jersey 08625-0600

Contract Amount:  N/A

Funding Source:  New Jersey Department of Transportation                

Contract Period:  Until Completion of State Project

Contract Basis: (   ) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS  

(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ

(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (X) n/a

Additional Information:

No municipal funds are required or will be spent under this agreement

body

 

WHEREAS, the State of New Jersey, through the New Jersey Department of Transportation (NJDOT or State) is in a process to undertake the design and construction of Route 280, Route 280 Westbound Ramp Over  1st and Orange Streets, Newark Subway and New Jersey Transit in the City of Newark, Essex County (hereinafter “the State Project” or “Project”); and

 

WHEREAS, the State Project may require the protection, relocation, rearrangement or adjustment of existing utility facilities, and the construction of new utility facilities of the Water and Sewer System owned and operated by the City of Newark (City); and

 

WHEREAS, the City’s legal right to occupy the public right-of-way, subject to the conditions imposed by NJDOT, is in no way changed or mitigated by this Agreement; and

 

WHEREAS, the City of Newark is not obligated under State law or by this Agreement, to relocate its own utility facilities at its own expense for this type of State Project; and

 

WHEREAS, the provisions of the State’s Accommodation of Utilities within Highway Right-of-Way N.J.A.C. 16:25 and Code of Federal Regulations, 23 C.F.R. 645, Subpart B are applicable; and

 

WHEREAS, the City shall cooperate with the State in developing plans and cost estimates for the work necessitated by the State Project and the City shall designate a responsible representative from its Department of Water and Sewer Utilities, to coordinate its efforts with those of the State; and

 

WHEREAS, the State will supply the City with a copy of the contract plans and specifications once the State Project is advertised.

 

NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL     OF THE CITY OF NEWARK, NEW JERSEY, THAT:

 

1.                     The Mayor and/or his designee the Director of the Department of Water and Sewer Utilities, are hereby authorized on behalf of the City of Newark to enter into a Utility Relocation Agreement with the New Jersey Department of Transportation (NJDOT) for the proposed Interchange Improvements to Route 280 Westbound Ramp over First and Orange Streets, Newark Subway and New Jersey Transit.

 

2.                     A fully executed copy of this Agreement shall be filed in the Office of the City Clerk by the Director of Water and Sewer Utilities.

 

3.                     No changes shall be made to the terms and conditions of this Agreement without prior Municipal Council approval.

 

4.                     No municipal funds are required or will be spent under this Agreement or for this State Project. However, the State will reimburse the City for any costs incurred by the City, which are necessary to accomplish this State Project.

 

STATEMENT

 

This resolution authorizes the Mayor and/or his designee, the Director of the Department of Water and Sewer Utilities, to enter into a Utility Relocation Agreement with the New Jersey Department of Transportation (NJDOT) for the  protection, relocation, rearrangement, adjustment  and/or replacement of the facilities of the City’s existing Water and Sewer System, and the construction of new facilities, as may become necessary during the State’s Project to make improvements to Route 280 Westbound Ramp Over First and Orange Streets, Newark Subway and New Jersey Transit.