File #: 19-0560    Version: 1 Name: Tomco Change Order
Type: Resolution Status: Adopted
File created: 3/27/2019 In control: Economic and Housing Development
On agenda: 7/23/2019 Final action: 7/23/2019
Title: Dept/ Agency: Economic and Housing Development Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order/Amend Contract Purpose: To complete unforeseen field conditions for construction of Riverfront Park Expansion-Phase C, increase contract amount, and extend contract completion date. Entity Name: Tomco Construction, Inc. Entity Address: 22 Howard Boulevard, Suite 204, Mt. Arlington, New Jersey 07856 Contract Amount: Not to exceed $8,293,382.24 Funding Source: 2016 Budget/Department of Economic and Housing Development Contract Period: Contract completion date extended from November 16, 2018 to June 19, 2020 Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A Additional Information: Original Resolution 7R2-a (s/as) was adopted on September 25, 2018 for a contract amou...
Related files: 18-0775
Title
Dept/ Agency: Economic and Housing Development
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Contract
Purpose: To complete unforeseen field conditions for construction of Riverfront Park Expansion-Phase C, increase contract amount, and extend contract completion date.
Entity Name: Tomco Construction, Inc.
Entity Address: 22 Howard Boulevard, Suite 204, Mt. Arlington, New Jersey 07856
Contract Amount: Not to exceed $8,293,382.24
Funding Source: 2016 Budget/Department of Economic and Housing Development
Contract Period: Contract completion date extended from November 16, 2018 to June 19, 2020
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Original Resolution 7R2-a (s/as) was adopted on September 25, 2018 for a contract amount not to exceed $8,154,999.00.
Change Order #1 will increase the contract amount by $138,383.24, for a total contract amount not to exceed $8,293,382.24 and extend the contract completion date June 19, 2020.
body

WHEREAS, Resolution 7R2-a (S/A.S.), adopted September 25, 2018, authorized the Director of the Department of Economic and Housing Development, 920 Broad Street, Newark New Jersey 07102, to enter into and execute the Contract for constructing Riverfront Park Expansion - Phase C with Tomco Construction, Inc. (the "Contract"), 22 Howard Boulevard, Suite 204, Mt. Arlington, New Jersey 07856, for the total bid amount of $8,154,999.00; and

WHEREAS, due to unforeseen conditions at the time of the design, the following change order is requested: Change Order No. 1 - (a) Request by Army Corp of Engineers to install a 6" underdrain pipe system, (b) Request by adjacent property owner ("Matrix") for stone spread across staging area, and (c) an ...

Click here for full text