File #: 09-1155    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 7/30/2009 In control: Engineering
On agenda: 9/2/2009 Final action: 9/2/2009
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolutions #7R-x 080107 and 7R4-e 091708 Purpose: Additional compensation and extension of contract period for project known as Broad Street Streetscape-Phase II Entity Name: Berto Construction, Inc. Entity Address: 625 Leesville Avenue, Rahway, NJ 07065 Original Contract Amount (Resolution #7R-x 080107): $3,394,057.43 Change Order #1 (Resolution #7R4-e 091708): $477,724.90 Change Order #2: $693,766.94 Total Contract Amount: $4,565,549.27 Funding Source: City of Newark Budget/Department of Engineering Contract Period: Contract period extended to September 30, 2009 Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) Non-Fair & Open ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: N/A
Title
Dept/ Agency: Engineering
Action:  (   ) Ratifying     (X) Authorizing     (X) Amending
Type of Service:  Change Order/Amend Resolutions #7R-x 080107 and 7R4-e 091708
Purpose: Additional compensation and extension of contract period for project known as Broad Street Streetscape-Phase II
Entity Name:  Berto Construction, Inc.
Entity Address:  625 Leesville Avenue, Rahway, NJ  07065
Original Contract Amount (Resolution #7R-x 080107):  $3,394,057.43
Change Order #1 (Resolution #7R4-e 091708): $477,724.90
Change Order #2:  $693,766.94
Total Contract Amount:  $4,565,549.27
Funding Source: City of Newark Budget/Department of Engineering
Contract Period:  Contract period extended to September 30, 2009
Contract Basis: (X) Bid   (   ) State Vendor  (   ) Prof.  Ser.  (   ) EUS   
(   ) Fair & Open (   ) Non-Fair & Open  (   ) RFP  (   ) RFQ  (   ) Private Sale
(   ) Grant  (   ) Sub-recipient   ( ) n/a
Additional Information:  N/A