File #: 20-0702    Version: 1 Name: Change Order #1 Phase-4(A) Lead Service Line Replacement Contract 20-WS2020 - Montana Construction Corp.
Type: Resolution Status: Adopted
File created: 6/15/2020 In control: Water Sewer Utility
On agenda: 6/24/2020 Final action: 6/24/2020
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order #1/Amend Resolution 7R12-a(S) adopted on December 10, 2019 Purpose: To execute Change Order #1 for Phase-4(A) Lead Service Line Replacement Contract 20-WS2020. Entity Name: Montana Construction, Inc. Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644 Contract Amount: Not to exceed $40,000,000.00 Funding Source: Water and Sewer Utilities Capital Budget/NW041-19W-19W00-94710-B2019 Contract Period: 280 days from Notice to Proceed to Final Completion, extended by 45 days Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient (X) N/A Emergency Declaration Additional Information: Original Resolution 7R12-a(S) adopted on December 10, 2019 awarded a contract in an amount not to exceed ...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order #1/Amend Resolution 7R12-a(S) adopted on December 10, 2019
Purpose: To execute Change Order #1 for Phase-4(A) Lead Service Line Replacement Contract 20-WS2020.
Entity Name: Montana Construction, Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Contract Amount: Not to exceed $40,000,000.00
Funding Source: Water and Sewer Utilities Capital Budget/NW041-19W-19W00-94710-B2019
Contract Period: 280 days from Notice to Proceed to Final Completion, extended by 45 days
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient (X) N/A Emergency Declaration
Additional Information:
Original Resolution 7R12-a(S) adopted on December 10, 2019 awarded a contract in an amount not to exceed $39,067,530.00.
Change Order #1 will increase the original contract amount by $932,470.00 for a total contract amount not to exceed $40,000,000.00 and extending completion time by forty-five (45) calendar days.

body

WHEREAS, Resolution 7R12-a(S) adopted on December 10, 2019 authorized the extension of emergency contract designated as E2019-11 for Contract 20-WS2020 Phase-4(A) Lead Service Line Replacement, with Montana Construction Inc., 80 Contant Avenue, Lodi, New Jersey 07644, in the amount of $39,067,530.00, in accordance with Ordinance 6PSF-e adopted on April 6, 2011, Article 2:5-13.2(E)(1) and N.J.S.A. 40A:11-6.; and

WHEREAS, during the course of the Project, additional Police Traffic Control costs were incurred under Contract 20-WS2020 in the net amount of $932,470.00 in order to complete the Project; and

WHEREAS, Contract 20-WS2020, therefore, is to be amended with a net amount of $932,470.00 to be added to the total contract amount; and

...

Click here for full text