File #: 22-0189    Version: 1 Name: Resolution: Closeout Change Order #1 - Phase-1(A) - Contract 11-WS2017 (Re-bid) - Montana Construction Corporation, Inc.,
Type: Resolution Status: Adopted
File created: 2/14/2022 In control: Water Sewer Utility
On agenda: 4/6/2022 Final action: 4/6/2022
Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Final Quantities Change Order #1/Amend Resolution #7R12-a adopted on February 6, 2019 Purpose: To execute Contract Close out Change Order #1 Phase-1(A) Sewer Cleaning and Rehabilitation - Contract 11-WS2017 (Re-bid). Entity Name: Montana Construction Corporation, Inc. Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644 Contract Amount: Not to exceed $2,341,776.90 Funding Source: Capital Budget/Department of Water and Sewer Utilities Contract Period: 834 calendar days to final completion from the date of the issuance of a written Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-a adopted on February 6, 2019 authorized a contract in...
Sponsors: Council of the Whole
Related files: 18-1898
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Final Quantities Change Order #1/Amend Resolution #7R12-a adopted on February 6, 2019
Purpose: To execute Contract Close out Change Order #1 Phase-1(A) Sewer Cleaning and Rehabilitation - Contract 11-WS2017 (Re-bid).
Entity Name: Montana Construction Corporation, Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Contract Amount: Not to exceed $2,341,776.90
Funding Source: Capital Budget/Department of Water and Sewer Utilities
Contract Period: 834 calendar days to final completion from the date of the issuance of a written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a adopted on February 6, 2019 authorized a contract in the amount of $2,669,111.00 for a period of (320) calendar days from the date of the issuance of a written Notice to Proceed.

Contract Close out Change Order #1 will reduce the contract amount by $327,334.10 for a new total contract amount not to exceed $2,341,776.90 and increase the contract period by (514) calendar days for a new completion period of (834) calendar days from the date of the issuance of a written Notice to Proceed.
body

WHEREAS, Resolution 7R12-a adopted on February 6, 2019, authorized the award of Contract 11-WS2017 (Re-bid) to Montana Construction Corporation, Inc., 80 Contant Avenue, Lodi, New Jersey 07644, in the amount of $2,669,111.00, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, the Contract 11-WS2017 (Re-bid), was completed with a net reduction of Three Hundred Twenty-Seven Thousand Three Hundred Thirty-Four Dollars and Ten Cents ($327,334.10) due to final quantity adjustments and an addit...