Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolutions #7R-x 080107 and 7R4-e 091708
Purpose: Additional compensation and extension of contract period for project known as Broad Street Streetscape-Phase II
Entity Name: Berto Construction, Inc.
Entity Address: 625 Leesville Avenue, Rahway, NJ 07065
Original Contract Amount (Resolution #7R-x 080107): $3,394,057.43
Change Order #1 (Resolution #7R4-e 091708): $477,724.90
Change Order #2: $693,766.94
Total Contract Amount: $4,565,549.27
Funding Source: City of Newark Budget/Department of Engineering
Contract Period: Contract period extended to September 30, 2009
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) Non-Fair & Open ( ) RFP ( ) RFQ ( ) Private Sale
( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information: N/A