Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( X ) Amending
Type of Service: Professional Services Contract
Purpose: Delancy Street Roadway Improvements, Final Design Project, Change Order No. 3 to Contract No. 06-2011PS
Entity Name: Michael Baker Jr., Inc.
Entity Address: One Gateway Center, Suite 2330, Newark, New Jersey 07102
Contract Amount: Increased by $201,515.00 (Change Order Amount) thereby bringing the total amount of this contract to $1,394,352.00
Funding Source: NJDOT/FHWA
Contract Period: Extended to November 1, 2014 to November 1, 2015
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Original contract-$1,192,837.00 + Change Order #3 - $201,515.00= New Contract Total-$1,394.352.00. Note: Change Orders 1 & 2 extended the dates of completion.
body
WHEREAS, Resolution 7R4-C, adopted September 8, 2011, authorized the Director of the Department of Engineering to accept the proposal dated August 9, 2010 and revised August 23, 2010 submitted by Michael Baker Jr. Inc., One Gateway Center, Suite 2330, Newark, New Jersey 07102, and execute Contract No. 06-2011PS, for the Delancy Street Roadway Improvements, Final Design Project, in the amount not to exceed $1,192,837.00; and
WHEREAS, the original contract term was 365 days from the effective date of the issuance of the Notice to Proceed, or November 3, 2011 through November 2, 2012; and
WHEREAS, Resolution 7R4-A, adopted January 16, 2013, authorized the Director of the Department of Engineering to issue and execute Change Order No. 1/Contract Amendment, to Contract No. 06-2011PS, for the Delancy Street Roadway Improvements, Final Design Project, which authorized a one (1) ye...
Click here for full text