File #: 15-2019    Version: 1 Name: Delancy St Final Design, Change Order # 4
Type: Resolution Status: Filed
File created: 10/23/2015 In control: Engineering
On agenda: 1/20/2016 Final action: 1/20/2016
Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing ( ) Amending Type of Service: Professional Services Contract Purpose: Change Order No.4, Delancy Street Roadway Improvements, Final Design, Contract No. 06-2011PS Entity Name: Michael Baker Jr., Inc. Entity Address: One Gateway Center, Suite 2330, Newark, New Jersey 07102 Contract Amount: $1,394,352.00 Funding Source: Department of Engineering Budget 2015 Contract Period: One (1) year extension of the term of the contract, from November 1, 2015 through November 1, 2016 Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Addition Information: A one (1) year extension of the term of the contract from November 1, 2015 through November 1, 2016, at no additional cost to the City of Newark.
Sponsors: Council of the Whole
Related files: 20-0518, 11-0866, 23-0075, 14-0045, 15-0795, 14-1291
Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing ( ) Amending
Type of Service: Professional Services Contract
Purpose: Change Order No.4, Delancy Street Roadway Improvements, Final Design, Contract No. 06-2011PS
Entity Name: Michael Baker Jr., Inc.
Entity Address: One Gateway Center, Suite 2330, Newark, New Jersey 07102
Contract Amount: $1,394,352.00
Funding Source: Department of Engineering Budget 2015
Contract Period: One (1) year extension of the term of the contract, from November 1, 2015 through November 1, 2016
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
A one (1) year extension of the term of the contract from November 1, 2015 through November 1, 2016, at no additional cost to the City of Newark.

body

WHEREAS, Resolution. 7R4-C, adopted September 8, 2011, authorized the Director of the Department of Engineering to accept the proposal submitted by Michael Baker Jr. Inc., One Gateway Center, Suite 2330, Newark, New Jersey 07102, and execute Contract No. 06-2011PS, for the Delancy Street Roadway Improvements, Final Design Project, in the amount not to exceed $1,192,837.00; and

WHEREAS, the original contract term was 365 days from the effective date of the issuance of the Notice to Proceed, from November 3, 2011 through November 2, 2012; and

WHEREAS, Resolution 7R4-A, adopted January 16, 2013, authorized the Director of the Department of Engineering to issue and execute Change Order No. 1/Contract Amendment, to Contract No. 06-2011PS, for the Delancy Street Roadway Improvements, Final Design Project, which authorized a one (1) year extension of term of the contract, from November 3, 2012 to November 2, 2013; and

WHEREAS, Resolution 7R4-A, adopted Ma...

Click here for full text