Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Professional Services Contract
Purpose: Contract Modification for Delancy Street Drainage, Traffic and Roadway Improvements (Final Design) Project Contract No. 06-2011PS
Entity Name: Michael Baker International, Inc.
Entity Address: One Gateway Center, Suite 2330, Newark, New Jersey 07102
Contract Amount: Increasing contract amount by $345,490.61, with an amended not to exceed amount of $2,337,818.61
Funding Source: New Jersey Department of Transportation (NJDOT),
NW 051 - G23 - 71280 - B2023
Contract Period: One (1) year from the date of a Notice to Proceed
Contract Basis: ( ) Bid ( ) State Vendor ( x ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
This amendment modifies Resolution 7R3-a adopted on August 05, 2020, by increasing the Michael Baker International, Inc. contract amount by an additional $345,490.61 and extending the contract term to one (1) year from the date of a Notice to Proceed, with a total project cost of $2,337,818.61.
Body
WHEREAS, the City of Newark, Department of Engineering, has determined that Delancy Street, between Avenue I and Rutherford Street, is in need of major reconstruction; and
WHEREAS, on September 8, 2011, the Municipal Council adopted Resolution 7R4-c, authorizing the Director of the Department of Engineering to accept the proposal submitted by Michael Baker International, Inc., One Gateway Center, Suite 2330, Newark, New Jersey 07102, dated August 9, 2010 and revised August 23, 2010, and to execute Contract No. 06-2011PS, for the Delancy Street Roadway Improvements, Final Design Project, in the amount not to exceed $1,192,837.00; and
WHEREAS, the original contract term was 365 days from the e...